The status of new businesses and development coming to Thurmont:

Subdivisions

        Hobb’s Division (East Main Street) — Final plat recorded for two lots in Mixed-Use Village 1.

Hammaker Hills, Phase 1 (Woodland Avenue) — Final plat recorded for 37 single-family lots in R-2 district. Ten permits issued.

Hammaker Hills, Phase 2 (Westview Drive): Preliminary plat approved for 22 single-family lots in R-2 district. The improvement plan is conditionally approved.

        Mechanicstown, LLC (Emmitsburg Road) — Preliminary plat approved for 31 single-family lots in R-2/ ARP district.

        Mountain Brooke (Emmitsburg Road) — Preliminary plat approved for 11 single-family lots in R-2/ ARP district.   

        Meunier Minor Subdivision (North Carroll Street) — Preliminary/final plat approved for one new lot and adjustment of two lots in R-2 district.

        Simmer’s Minor Subdivision (Apples Church Road) — Preliminary/final plat approved for one single-family lot.

        Oak Forest Townhouse Community (East Moser Road) — Concept plan submitted for a 36-unit townhouse community in R-5 district.

        505 E. Main St. Minor Subdivision (E. Main Street) — Preliminary/final plat approved for one lot.

Simmer’s Subdivision (Apples Church Road): Concept plan submitted for a 40-unit townhouse community in R-5 district.

Site Plans

        Weis Gas & Go (2 Thurmont Blvd.) — Weis Markets did a partial site redevelopment; a Gas & Go fuel station to consist of three pumps and one manned kiosk is under construction.

Thurmont Business Park (Thurmont Blvd.) — Lot 1 to be developed for the relocation of Goodwill into a 17,850-square-foot building; final site plan is under review.